Thursday, 04 January 2007 01:33

Bypass Opening Delayed Until Mid- February

slide13A new schedule has been announced for the opening of the Hwy 49 Bypass of Sutter Creek and Amador City. According to Project Manager Scott Maas, the Sutter Creek Bridge false work is still being removed, slowly, and it is now estimated to be mid-February before the Bypass will be ready to open. Maas states that The removal of the current section of false work will be completed this week. The removal of the last section, Span #1, will begin this week and will take approximately 4 weeks to accomplish. Maas indicates that this delay is not being caused by lack of equipment or personnel; instead he states “it is just time consuming to remove the false work carefully and safe! The bridge railing is expected to be completed in the next 2 to 3 weeks.
Maas states that The PG&E gas line extension is still under construction as well There is approximately 400 feet of trenching required with a depth of approximately 4 to 6 feet that needs to be completed. This work is located between Valley View and the highway and will be in the shoulder of the roadway. Natural gas to existing customers will not be interrupted and Maas emphasizes that this work does not affect the Bypass from opening to traffic. It is anticipated that this work will be completed within the next 3 weeks. The Bypass Contractor was given 46 extra working days for the blasting work that was unforeseen when the initial bids were approved for the project. The extra days were given due to “efficiency” to complete the work. The opening of the bypass in Mid February will coincide with the expiration of the contract around mid-February, plus the addition of rain days.