Thursday, 04 January 2007 01:33
Bypass Opening Delayed Until Mid- February
Maas
states that The PG&E gas line extension is still under construction as well
There is approximately 400 feet of trenching required with a depth of approximately
4 to 6 feet that needs to be completed. This work is located between Valley
View and the highway and will be in the shoulder of the roadway. Natural gas to
existing customers will not be interrupted and Maas emphasizes that this work
does not affect the Bypass from opening to traffic. It is anticipated that
this work will be completed within the next 3 weeks. The Bypass Contractor was
given 46 extra working days for the blasting work that was unforeseen when the
initial bids were approved for the project. The extra days were given due to
“efficiency” to complete the work. The opening of the bypass in Mid February
will coincide with the expiration of the contract around mid-February, plus the
addition of rain days.

