The idea between the three counties, when the alliance
was formed, was to better the chances of each county to receive funds for their
individual projects by pooling transportation funds and appealing to the
California Transportation Commission’s ideals that encourage such alliances. The plan worked and the first project funded was the Sutter Creek
Bypass. Currently, with the
Sutter Creek project nearing completion, the Angel’s Camp project is set to
move forward- only one problem cost overruns which have pushed the originally
28 million dollar project to the 60 million dollar mark. The 13.5
million dollar deficit was the final straw for partner Amador and Alpine County
who began to ask Caltrans officials why the cost increases were escalating so
dramatically, particularly on the Angel’s project.
Unsatisfied with the
answers, the coalition began to wage a campaign of words with Calaveras County
Officials lashing out at the partners worried they would loose their project in
Angel’s Camp. The issue amongst the partners was concern over the amount of
future funding that each partner would be giving up for state funding
allocations expected after 2012. The state was looking at the 13.9 million dollars as a loan to the tri
county alliance, a loan that would be paid back to the state with future
allocations being reduced or eliminated. The alliance had recently met
and Caltrans proposed a funding plan which includes the usage of the Prop 1B
funds also called the Corridor Mobility Improvement Account. Cal Trans proposal was a cost
sharing approach which includes 3.2 million dollars from the Cal Trans
Discretionary STIP, or State Transportation Improvement Program funds,
5.2 million from the Tri-County STIP Augmentation, and finally a 4.4 million
dollar funding request from the Corridor Mobility Improvement Account.
Field explains that “In
proposition 1B the voters approved additional funding for the State
Transportation Improvement Program. Our share of that amount would be about 10
million under normal circumstances. These are not normal circumstances because the law was
written such that the State doesn’t have to consider this money subject to the
share formulas—so instead we have to compete for it, and we are doing that.” To only complicate things further Field
explains, “This money is
only available pending the sale of bonds and the state can only sell so many
bonds each year so we don’t know for sure when this money, if its awarded to
us, will actually be available.”
Field also noted that the number in question is not 10 million dollars
because the Tri-County’s owe 3 to 4 million dollars of their shares for the
Angels Camp Bypass cost increases.
Last night the Calaveras Council of Governments received a report from Project Manager Scott Maas that the $13.9 million figure he had been reporting to them "is incorrect. The Tri-Counties have borrowed only $3.4million of future State Transportation Improvement Project funds." The California Transportation Commission will vote on the Caltrans/Tri-County Proposal for the resolution of the issue on February 28th.