He indicated that Alpine, Amador, and Calaveras’ cost will be similar to
what was previously developed in the Cal Trans Cost sharing approach, however
that approach did include the granting of the CMIA funding request of $4.4
million dollars, therefore, somebody has got to cover the cost gap.
Field said they are proposing
that the Tri-County’s pay $5.192 million and that Cal Trans pay $7.648 million
adding up to a total of $12.84 million dollars. “So, we are roughly splitting
it,” said Field. Additionally
Cal Trans share would include another one million dollars to bring the old Hwy.
49 up to standard before it is turned over.
Again Sutter Ione Road is left out of the funding mix, as Supervisor Forster requested that the County pursue funding to repair the road which was badly damaged during the construction of the Hwy. 49 bypass. The County still has said that they might pursue a claim for damages against the state. In the meantime Field said that Cal Trans District 10 is supporting the proposal however that is only step two of Plan B. “We are half way there. Step one is by getting the County’s together, Cal Trans support is the second step, and the 3rd is getting approval from Cal Trans Head quarters, the 4th step is the CTC’s approval,” Field stated.
The Tri Counties intend to present
the proposal to Cal Trans Headquarters “within the next few weeks” and if
approval is given, they will appear before the California Transportation
Commission on March 15 to get the final say as to whether the cost
sharing approach with Cal Trans and the Tri-Counties is a go. Field indicated
that if they get Cal Trans Headquarters approval then it is likely the CTC will
also approve of the cost sharing approach. He said that normally they would present the proposal in
April and the CTC would allocate those monies in June, but “we are going to
plead with them because we need to start (the Angels Camp Bypass) this summer,”
said Field.
The
Tri-County’s hope to have the project out to bid in June, before the rest of
the CTC approved projects such as the Willets and Brawley Bypass projects take
all the available and qualified contractors. The big question now is: What happens if the
California Transportation Commission does not approve the proposal? Charles
Field says, “Good question. If they say no to the plan then the Angels Camp
Bypass is at risk and we will have to try to find a Plan C; and right now we
don’t know what that is.” Field did say however, that “Amador’s commitment to help
Calaveras is very real. They helped us fund the Hwy. 49 bypass and now it’s
about to open to traffic. Calaveras is worried Alpine and Amador (might) back
out on helping them finish the Angels Camp Bypass. I don’t think that is going
to happen.”

